For the following schedule, draw the node network, perform the CPM calcula-
tions, mark the critical path, and complete the table.
Activity
Duration
IPA
ES
EF
LS
LF
TF
FF
A
2
-
B
7
A
C
10
A
D
5
A
E
4
B
F
4
B, C
G
3
C
H
6
C, D
I
3
D
J
6
E, F, G
K
8
F, G, H
L
5
H, I
M
3
K, L