3.
For the following schedule, draw the node network, perform the CPM
calculations, mark the critical path, and complete the table.
Activity
Duration
IPA
ES
EF
LS
LF
TF
FF
A
2
-
B
4
A
C
6
A
D
9
A
E
5
B
F
7
B, C
G
3
D, E, F
4.
For the following schedule, draw the node network, perform the CPM
calculations, mark the critical path, and complete the table.
Activity
Duration
IPA
ES
EF
LS
LF
TF
FF
A
6
-
B
2
-
C
8
A
D
5
A, B
E
3
B
F
6
D, E
G
5
C, D
H
2
F, G
5.
For the following schedule, draw the node network, perform the CPM
calculations, mark the critical path, and complete the table.
Activity
Duration
IPA
ES
EF
LS
LF
TF
FF
A
6
-
B
2
-
C
9
-
D
4
A, B
E
7
B
F
5
D
G
10
D, E
H
8
C, F, G
I
3
C, G
J
2
H, I