Letter 57
To employer, if possession not given on the due or the deferred date (a)
This letter is not suitable for use with MW or MWD or GC/Works/1
(1998).
Special delivery
Dear
[ If deferment of possession clause does not apply: ]
Possession of the site should have been given to us on [ insert date ]in
accordance with clause 2.4 [ substitute '2.3' when using DB ] of the conditions of
contract. Possession was not given to us on the due date.
[ If deferment of possession clause does apply, but deferred date not met: ]
Under clause 2.5 [ substitute clause '2.4' when using DB ] you deferred the giving
of possession until [ insert date ]. You did not give us possession on the deferred
date.
[ Then either: ]
Moreover, the architect has informed us today by telephone that the date for
possession remains uncertain.
[ Or: ]
The architect has informed us today by telephone that you will be unable to
give possession until [ insert date ].
[ continued ]