Letter 295
To sub-contractor, notifying practical completion after earlier dissent
Dear
Take this as notice under clause 2.20.2 [ substitute '2.14.2' when using
ICSub/C, ICSub/NAM/C or ICSub/D/C or '14.2' when using GC/Works/SC ]of
the sub-contract that practical completion [ substitute 'completion' when using
GC/Works/SC ] of the sub-contract works took place on the [ insert date ]. Practical
completion [ substitute 'completion' when using GC/Works/SC ] shall be deemed
for all the purposes of the sub-contract to have taken place on that date.
Yours faithfully