Letter 294
To sub-contractor, if contractor dissents from date of
practical completion
Dear
We are in receipt of your notification dated [
insert date which should not be more
the 14 days before the date of this letter
] stating that, in your opinion, practical
completion [
substitute 'completion' when using GC/Works/SC
] of the sub-contract
[
insert nature of works
] works will be achieved on [
insert date
].
Take this as formal notice, in accordance with clause 2.20.1 [
substitute
'2.14.1' when using ICSub/C, ICSub/NAM/C or ICSub/D/C or '14.1' when using
GC/Works/SC
] of the sub-contract, that we dissent from such date of practical
completion [
substitute 'completion' when using GC/Works/SC
] for the following
reasons:
[
State reasons clearly, but briefly.
]
Yours faithfully