Civil Engineering Reference
In-Depth Information
Letter 249
To sub-contractor, accepting Schedule 2 quotation
This letter is only suitable for use with SBCSub/C, SBCSub/D/C or
DBSub/C.
Dear
Thank you for your Schedule 2 quotation dated [
insert date
] which we
requested in accordance with clause 5.3 when we issued direction number
[
insert number
] dated [
insert date
].
We accept your quotation. Note that you are to carry out the work.
[
Add, as applicable:
]
The amount of the adjustment to the sub-contract sum is [
insert amount
].
The amount to be taken into account in calculating the final sub-contract sum
is [
insert amount
].
The amount under paragraph 2.3 is [
insert amount
].
The amount under paragraph 2.4 is [
insert amount
].
[
Add, if applicable, either:
]
The revised period for completion of the sub-contract Works is [insert period].
[
Or:
]
There will be no change to the period for completion of the sub-contract Works.
Yours faithfully