Letter 240
To sub-contractor, requiring compliance with direction
Special delivery
Dear
Take this as notice under clause 3.6 [ substitute '4.1' when using GC/Works/SC ]of
the conditions of sub-contract that we require you to comply with our direction
number [ insert number ] dated [ insert date ], a further copy of which is enclosed.
If within 7 days of receipt of this notice you have not begun to comply, we
will employ and pay others to comply with such direction. An appropriate
deduction, which in this instance will amount to all costs incurred in
connection with such employment, will be taken into account in the
calculation of the final sub-contract sum or will be recovered from
you as a debt.
Yours faithfully
Copy: Architect