Letter 193
To employer, where either party may terminate
This letter is not suitable for use with GC/Works/1 (1998).
Special delivery
Dear
The carrying out of the whole or substantially the whole of the uncompleted
Works has been suspended for a continuous period of [ insert the relevant period
from the contract particulars or insert 'one month' when using MW or MWD ]by
reason of the following event(s): [ insert details of the event(s) ].
Take this as notice, in accordance with the provisions of clause 8.11.1 [ substitute
'6.10.1' when using MW or MWD ] of the conditions of contract, that unless the
suspension ceases within 7 days of receipt of this notice, we may terminate our
employment under the contract.
Yours faithfully