Letter 187
To employer or architect, if default notice served justly
This letter is not suitable for use with GC/Works/1 (1998).
Special delivery
Dear
We are in receipt of your letter of the [ insert date ] which you sent as a default
notice in accordance with clause 8.4.1 [ substitute '6.4.1' when using MW or
MWD ] of the conditions of contract.
We regret that you have felt it necessary to send such a notice, but we are
pleased to be able to inform you that [ insert whatever steps are being taken to
remove the default ].
Yours faithfully
Copy: Architect/employer [ delete as appropriate ]