Civil Engineering Reference
In-Depth Information
Letter 183
To architect, if ascertainment too small
This letter is not suitable for use with MW, MWD or DB.
Dear
We refer to our notice dated [
insert date
] in respect of loss and/or expense
[
substitute 'expense' when using GC/Works/1 (1998)
]. Your [
substitute 'The quantity
surveyor's' when using GC/Works/1 (1998)
] letter of the [
insert date
] notifying us
of the amount ascertained appears to take little account of the very full
supporting information submitted by us on [
insert date or dates
].
Unless we hear from you by [
insert date
] that you will amend your
ascertainment to take account of the information we have supplied, a
dispute will have arisen which we will refer to adjudication in due course.
Yours faithfully