Letter 174
To architect, applying for payment of loss and/or expense (a)
This letter is not suitable for use with MW, MWD or GC/Works/1
(1998).
Dear
We hereby make application under clause 4.23 [
substitute '4.17' when using IC
or ICD or '4.19' when using DB
] of the conditions of contract as follows:
We have incurred/are likely to incur [
delete as appropriate
] direct loss and/or
expense and financing charges in the execution of this contract for which we
will not be reimbursed by a payment under any other provision in this
contract, because the regular progress of the Works has been/is likely to be
[
delete as appropriate
] materially affected by [
describe and unless referring to
deferment of possession, add:
] being a relevant matter in clause [
insert clause
number
].
Yours faithfully