Letter 162
To architect, if extension of time is insufficient
Dear
We have received today your notification of an extension of time of [ insert
period ] producing a new date for completion of [ insert date ].
We find your conclusions inexplicable in the light of the facts and the
information we submitted in support of those facts.
Perhaps you would be good enough to reconsider your grant of extension of
time or let us have an indication of your reasons for arriving at the time period
you have granted.
Yours faithfully