Letter 130
To architect, if antiquities found
This letter is not suitable for use with IC, ICD, MW or MWD.
Dear
We have today uncovered [ describe ] which we consider falls within the
provisions of clause 3.22 [ substitute '3.15' when using DB or '32(3)' when using
GC/Works/1 (1998) ]. It lies at a depth of [ insert precise depth ] below [ insert some
nearby permanent point from which measurement taken ]at[ describe location e.g. '2
metres west of proposed inspection chamber 23' ].
We have stopped work in the vicinity and erected a temporary wooden fence
and waterproof cover. We should be pleased to receive your immediate
written instructions.
[ If using SBC or DB, add: ]
The progress of the Works is being delayed by the above circumstances which
we consider to be a relevant event under clause 2.29.2.1 [ substitute '2.26.2.1'
when using DB ]. When the delay is finished we will furnish you with our
estimate of delay in the completion of the Works and further supporting
particulars. You may be assured that we are using our best endeavours to
prevent delay in progress and completion of the Works. Please take this as
notice in accordance with clause 2.27.1 [ substitute '2.24.1' when using DB ]. We
further consider that we are entitled to reimbursement for direct loss and/or
expense under the provisions of clause 3.24 [ substitute '3.17' when using DB ].
[ continued ]