Letter 83
To architect, if discrepancy found between Employer's Requirements
and Contractor's Proposals
This letter is only suitable for use with contractor's designed portion
of SBC or ICD or DB.
Dear
We have found a discrepancy between the Employer's Requirements and our
Contractor's Proposals [ give details ]. The contract does not expressly deal with
this situation. If you are content to accept the way we have dealt with the
matter in our Contractor's Proposals, there is no problem, otherwise we
suggest that a meeting on site is required. Please let us have your response
as soon as possible/as a matter of urgency [ delete as appropriate ].
Yours faithfully