Typical productivity for costing (Queensland Australia).
Drilling
Soil
Soft rock
Hard rock
Land based drilling
20 m/day
15 m/day
10 m coring/day
Cone penetration testing
(excludes dissipation testing)
100 m/day
Not applicable
Not applicable
(Highly dependent on weather/tides/location)
Non Cyclonic Months
Cyclonic Month
Floating
barge
Open water
Land based
50%
Land based
30%
Sheltered water
Land based
70%
Land based
50%
(Dependent on weather/location)
Non Cyclonic Months
Cyclonic Month
Jack up
barge
Open water
Land based
70%
Land based
50%
Sheltered water
Land based
90%
Land based
70%
•
Over water drilling costed on daily rates as cost is barge dependent rather than
metres drilled.
•
Jack up barge has significant mobilisation cost associated - depends on location
from source.
1.16 Site investigation costs
•
Often an owner needs to budget items (to obtain at least preliminary funding).
The cost of the SI can be initially estimated depending on the type of project.
•
The actual SI costs will then be refined during the definition of needs phase
depending on the type of work, terrain and existing data.
•
A geo-environmental investigation is costed separately.
Table 1.16
Site investigation costs (Rowe, 1972).
Type of work
% of capital cost of works
% of earthworks and foundation costs
Earth dams
0.89-3.30
1.14-5.20
Railways
0.60-2.00
3.5
Roads
0.20-1.55
1.60-5.67
Docks
0.23-0.50
0.42-1.67
Bridges
0.12-0.50
0.26-1.30
Embankments
0.12-0.19
0.16-0.20
Buildings
0.05-0.22
0.50-2.00
Overall mean
0.7
1.5