Geoscience Reference
In-Depth Information
Table 1.15 Typical productivity for costing (Queensland Australia).
Drilling
Soil
Soft rock
Hard rock
Land based drilling
20 m/day
15 m/day
10 m coring/day
Cone penetration testing
(excludes dissipation testing)
100 m/day
Not applicable
Not applicable
(Highly dependent on weather/tides/location)
Non Cyclonic Months
Cyclonic Month
Floating
barge
Open water
Land based 50%
Land based 30%
Sheltered water
Land based 70%
Land based 50%
(Dependent on weather/location)
Non Cyclonic Months
Cyclonic Month
Jack up
barge
Open water
Land based 70%
Land based 50%
Sheltered water
Land based 90%
Land based 70%
Over water drilling costed on daily rates as cost is barge dependent rather than
metres drilled.
Jack up barge has significant mobilisation cost associated - depends on location
from source.
1.16 Site investigation costs
Often an owner needs to budget items (to obtain at least preliminary funding).
The cost of the SI can be initially estimated depending on the type of project.
The actual SI costs will then be refined during the definition of needs phase
depending on the type of work, terrain and existing data.
A geo-environmental investigation is costed separately.
Table 1.16 Site investigation costs (Rowe, 1972).
Type of work
% of capital cost of works
% of earthworks and foundation costs
Earth dams
0.89-3.30
1.14-5.20
Railways
0.60-2.00
3.5
Roads
0.20-1.55
1.60-5.67
Docks
0.23-0.50
0.42-1.67
Bridges
0.12-0.50
0.26-1.30
Embankments
0.12-0.19
0.16-0.20
Buildings
0.05-0.22
0.50-2.00
Overall mean
0.7
1.5
 
 
Search WWH ::