Geoscience Reference
In-Depth Information
Table 17.5 Granular materials for pipe beddings.
Pipe size
Maximum particle size
100 mm
10 mm
<
100-200 mm
15 mm
200-300 mm
20 mm
300-500 mm
30 mm
>
500 mm
40 mm
Proper compaction at the haunches of pipes is difficult to achieve and measure.
-
Pipes are usually damaged during construction and proper cover needs to be
achieved, before large equipment is allowed to cross over.
-
Typically 300mm minimum cover, but 750mm when subjected to heavy
construction equipment loads.
17.6 Compacted earth linings
The key design considerations for earth linings are adequate stability and
impermeability.
The low permeability criteria requires the use of materials with
>
30% clay
fines.
Density of 95% of Standard Maximum Dry Density typically used.
Control Tests of at least 1 per 1000m 3 placed would be required.
Table 17.6 Typical compacted earth lining requirements.
Depth of water
Canal design
Side slope (1V :H)
Side thickness
Bottom thickness
0.5 m
1V :1.5 H
0.75 m
0.25 m
1.5 m
1V :1.75 H
1.50 m
0.50 m
3.0 m
1V :2.0 H
2.50 m
0.75 m
17.7 Constructing layers on a slope
Inadequate compaction may result at the edges or near sloping faces. Large equip-
ments are unable to compact on steep slopes. Layers are placed either horizontally
or on a minor slope. Benching may be required to control the water run off, and
hence erosion.
Proper compaction requires moisture content of soil near to its plastic limit.
The thickness of placed layers is typically 0.40m (compacted) for a 10 tonne roller,
but depends on the type of material being placed.
The thickness of placed layers is typically 0.20m (compacted) for 3 tonne roller.
 
 
Search WWH ::




Custom Search