Geoscience Reference
In-Depth Information
application 13.4
A soft clay site is to be prepared for development by applying a surcharge sand
fill of 2m thick. Thickness soft clay is 6m. Groundwater level: 1m below surface.
The wet unit weight soft clay is 14 kN/m 3 , the dry unit weight sand: 16 kN/m 3 , and
porosity is 40%. Determine the required vacuum to be applied to prefabricated
vertical drains to obtain 80% consolidation in 4 months. With what means could
such a vacuum be applied? Drain distance 2 R = 1.4 m; drain diameter 2 r 0 = 0.07 m.
Coefficient of consolidation c v = 2x10 -7 m 2 /sec.
application 13.5
Prefabricated vertical drains with vacuum are applied to drain a site with a very
low c v . Determine the required vacuum to be applied to the vertical drains to obtain
80% consolidation in 120 days. Surface load is 32 kPa. Coefficient of
consolidation: c v = 2x10 -8 m 2 /s. Drain distance 2 R = 1.4 m. Drain diameter 2 r 0 =
0.07 m
application 13.6
Fig 13.8 shows settlement stages during preloading. Given C c / (1+ e 0 ) = 0.5,
C / (1+ e 0 ) = 0.025, t 0 = 180 days, ' II = 120 kPa, ' III = 80 kPa, the most optimistic
estimate of the period of grace is given. This is too optimistic, as explained in the
notes. Find a more realistic estimate by assuming the unloading is only effective
for 50%.
application 13.7
A fill, which imposes a load of 50 kN/m 2 , compresses a clay layer of 5 m thick.
Vertical drains are installed to accelerate the consolidation process. The drain
width is 0.1 m, drain thickness is 0.01 m.
Determine an equivalent drain radius r 0 , based on surface similarity.
Calculate the degree of consolidation U after 6 month, given c v = 2x10 -7 m 2 /s,
drain spacing 2 R = 2 m (see Fig 12.6).
Calculate the time required to obtain the same degree of consolidation if vertical
drains are not used, and only vertical consolidation occurs to the ground surface.
Search WWH ::




Custom Search