Civil Engineering Reference
In-Depth Information
1 Permit title
2 Permit number .
Reference to other relevant permits
or isolation certificates
3 Job location
4 Plant identification
6 Hazard identification - including
residual hazards and hazards introduced
by the work
5 Description of work to be done
and its limitations
7 Precautions necessary - person(s) who
carries out precautions, e.g. isolations, should
sign that precautions have been taken
8 Protective equipment (PPE)
10 Acceptance - signature confirming
understanding of work to be done, hazards
involved and precautions required. Also
confirming permit information has been
explained to all workers involved
9 Authorisation - signature confirming
that isolations have been made and
precautions taken, except where these can
only be taken during the work. Date and
time duration of permit
12 Hand back - signed by acceptor
certifying work completed. Signed by
issuer certifying work completed and
plant ready for testing and
recommissioning
11 Extension/shift handover procedures -
signatures confirming checks made that
plan remains safe to be worked upon, and
new acceptor/workers made fully aware of
hazards/precautions. New time expiry given
13 Cancellation - certifying work
tested and plan satisfactorily
recommissioned
(Signatures - names must be legible)
Figure 8.29
Typical hot work permit
of course and not for high risk operations such as hot
works.
Hot work permits should normally include as a
minimum:
wall or partition the opposite side must be examined for
combustible material, the need to provide fi re resistant
coverings where work is being undertaken adjacent to
immovable wooden structures. In addition the checklist
may well include the isolation of existing detection
systems and the requirement for the provision of fi re
fi ghting equipment and competent persons to operate it.
A key element that will also be included in the hot
work permit will be the sign-off following an examin-
ation of the area (at least one hour after cessation of hot
works) to ensure that there are no fi re risks remaining.
A sample of a hot work permit can be found in the
Appendix 8.1, together with a sample hot work checklist
at Appendix 8.2.
The issues relating to highly fl ammable liquids and
LPG have been covered at length in preceding sections
of this chapter; however, quite specifi c to construction/
maintenance operations is the use of items such as tar
boilers, which are invariably powered by gas cylinders.
Tar boilers (and similar equipment) should remain
at ground level remote from the building where reason-
ably practicable. However, where the risk assessment
The nature and location of the hot work to be
undertaken
The proposed start time and duration of the hot work
The limitation of time for which the permit is valid
The person in direct control of the hot works
The authorised signing off (completion and checks)
of the works.
Separate permit forms may be required for different
tasks such as hot work and entry into confi ned spaces
and therefore different information and records are likely
to be required.
The hot work permit used as part of the safe system
of work will also provide details on checks that will
need to be made prior to the commencement of the
work such as the area being cleared of loose combus-
tible material, if work is to take place on one side of a
 
Search WWH ::




Custom Search