The effort and energy needed to sustain a data warehouse does not end
when the project tasks are all complete. This chapter shares what is needed to
release the data warehouse for use and what steps are necessary to formally
wrap up the project. It also looks forward, describing what can be done to
encourage adoption of the data warehouse. Additional effort is also required
to keep the data warehouse running. Finally, the chapter explores what can
cause a data warehouse to fall short of expectations, and offers practical steps
to get things back on track.
Finishing the Project
The project has been underway for many weeks or possibly months. The
requirements have been gathered and the overall solution designed. The ETL
system was built and the data has been loaded and validated. A BI application
has been built to facilitate use of the data warehouse. Only a few more things
are needed to wrap up the project.
Recapping the BI Application Launch
Ideas for launching the BI application were introduced in Chapter 11.
These launch activities are some of the last tasks on the project. Highlights of
the launch activities include the following:
Marketing and communication to let potential users of the data warehouse
know that it is ready for use. These efforts can also help pique interest
by demonstrating how the data warehouse can support users with their
work.