Figures 3.18-A through 3.18-C contain a second site with different
topography. Four alternative locations for a building site are considered.
Alternate locations A and D are more gently sloping than locations B and
C and have desirable surface drainage patterns to more readily accom-
modate a structure or development.
111
111
110
110
109
109
108
108
C
107
B
107
104
104
A
103
103
102
102
100
D
100
100
100
1” = 40'-0”
100
1” = 40'-0”
Figure 3.18-a Site evaluation and preliminary
grading plan
Figure 3.18-B The location was selected because it affords
desirable views and has similar slope attributes to A in Fig-
ure 3.17-A. The location of A allows out-of-doors uses to
be developed on the gentler slopes to the left and slightly
downhill of the building site.
111
110
109
108
SHP=102.3
107
104
103
102.5
102
100
100
1” = 40'-0”
Figure 3.18-C The conceptual grading plan demonstrates
how the topography can be modified to accommodate the
proposed building area