Civil Engineering Reference
In-Depth Information
Example No. 1
On 2 February 2010, the Engineer issued revised drawings to show an
additional staircase between the Ground Floor and Basement Level 1.
The work detailed on the revised drawings constitutes a variation
which has resulted in additional concrete works, masonry, metalwork
and decoration.
The additional price to which the Contractor is entitled is £5,321.
A review of the above immediately raises the following questions:
1. How were the revised drawings issued?
2. Which drawings were revised and what are the revision numbers?
3. Why does this instruction constitute a variation?
4. Why does this result in an entitlement to additional payment?
5. How has the claimed sum been calculated?
A reviewer would therefore have diffi culty in reaching a determination
in the absence of such vital information. The following example shows a
more satisfactory approach:
Example No. 2
On 2 February 2010
1
, the Engineer issued revised drawings
2,3
to show an
additional staircase between the Ground Floor and Basement Level 1.
Sub - Clause 3.3
(Instructions of the Engineer)
4
provides that the
Engineer may issue modifi ed drawings and Sub-Clause 13.1
(Right to
1
Exhibit 1 - Drawing Issue No. D 023, dated 2 February 2010
2
Exhibit 2 - Drawing No. A - GF - 1001 Rev A
3
Exhibit 3 - Drawing No. A - B1 - 1001 Rev A
4
Exhibit 4 - Extract from the Conditions of Contract; Sub-Clause 3.3
Search WWH ::
Custom Search