Item
Description
Cost
Ref.
Quantity
Unit
Rate
( £ )
Total
( £ )
D
MEP Engineer: W
Greenwood
J.004
30
Days
95.89
2,876.70
E
Architectural and
Finishes Supervisor:
K Bracken
J.005
30
Days
95.89
2,876.70
F
Planning Engineer:
M Tindall
J.006
30
Days
109.58
3,287.40
G
Senior Quantity
Surveyor: B Cohen
J.007
30
Days
123.28
3,698.40
H
Quantity Surveyor: P
Vickery
J.008
30
Days
76.71
2,301.30
J
Project
Administrator: B
Kay
J.009
30
Days
54.79
1,643.70
Sub - Contractor ' s
Site Staff
K
MEP Project
Manager: T
Woodman
J.010
30
Days
142.39
4,271.70
L
MEP Engineer: N
Back
J.011
30
Days
83.27
2,498.10
M
Interior fi t - out Site
Manager: L Moody
J.012
30
Days
103.96
3,118.80
Site Staff: To Summary of Site-Establishment Costs
39,312.00
Checklist - Appendices; Calculations
1. Appendix reference and title.
2. Revision number and date.
3. Page numbers.
4. Item numbers.
5. Column headings clearly describe the column contents.
6. Explanatory notes.
7. Units clearly annotated.
8. Cross-references to substantiating documents.