Table 2-22 Guideline values for L1, L2, L3, n, H, p, S and q (SIA-198, Table 7) [218].
Max. excavation width [m]
3
6
10
15
Tunnel (clause 5 23 2)
L1 Face area [m]
2
3
5
5
L2 Advance area [m]
15
20
25
35
L3 Rearward area [m]
150
200
250
300
n
Number of rock bolts per running m tunnel
2
4
5
9
Excavated shafts (clause 5 23 3)
H
Working area
2
3
5
5
p
Number of rock bolts per running m shaft
6
12
18
27
Sunk vertical shafts (clause 5 23 4)
S
Working area [m]
6
6
6
6
q
Number of rock bolts per running m shaft
3
6
9
13
Table 2-23 Matrix of the excavation types and excavation classes for drill and blast (SIA-198, Table 6)
[218].
Excavation types
Excavation classes
I
II
III
IV
V
A
Full-face excavation
A I
A II
A III
A IV
A V
B
Top heading
B I
B II
B III
B IV
B V
C
Divided top heading
C III
C IV
C V
D
Side headings
D III
D IV
D V
Table 2-24 Excavation classes (AK) for drill and blast (simplified).
AK I
AK II
AK III
AK IV
AK V
L1...
< 9 rock bolts
< 9 rock bolts
mesh & shotcrete
< 1/3 U
steel arches
shotcrete > 1/3U
HEB rolled steel
sets +
Marciavanti
L2...
mesh & rock
bolts
against rock fall
27 rock bolts
mesh & shotcrete
< 1/3 U
> 27 rock bolts
mesh & shotcrete
> 1/3 U
L3... > 27 rock bolts
mesh & shotcrete
> 1/3 U
L1: Face area ........................ 5 m
L2: Advance area: ................ 35 m
L3: Backup area ................... 300 m
for excavated span b = 12 m
n: number of rock bolts per tunnel n = 9
u: circumference