One special case is obstruction due to water ingress, which almost always reduces performance.
Standard 198 [218] provides sample contract conditions, which have proved successful. A ba-
sic difference is made between obstruction, which is covered by items in the bill of quantities,
and changed deadlines because the deadlines in the contract can no longer be achieved.