Civil Engineering Reference
In-Depth Information
ρ d max   =  1.97 Mg/m 3
omc  =  13%
Percentage air voids  =  1.0
Answer
Exercise 14.2
A 2.5 kg rammer compaction test was carried out in a 105 mm diameter mould of
volume 1000 cm 3 and a mass of 1125 g.
Test results were:
Moisture content (%)
10.0
11.0
12.0
13.0
14.0
Mass of wet soil and mould (g)
3168
3300
3334
3350
3320
Plot the curve of dry density against moisture content and determine the test
value for ρ d max and omc.
On your diagram plot the zero and 5% air voids lines (take G s as 2.65). If the
percentage of gravel omitted from the test (particle specific gravity  =   2.73) was
10%, determine more correct values for ρ dmax and the omc.
Answer
From test:
ρ dmax   =  1.97 Mg/m 3 ;
omc  =  12%
Corrected values:
ρ dmax   =  2.03 Mg/m 3 ;
omc  =  11%
Exercise 14.3
An MCV test carried out on a soil sample gave the following results:
No. of blows, B
Penetration (mm)
1
38.0
2
45.1
3
64.0
4
72.3
6
78.1
8
80.1
12
81.0
16
81.5
24
81.7
32
81.7
48
81.7
Determine the MCV of the soil.
Answer MCV  =  7.5
Exercise 14.4
An MCV test carried out on a glacial till gave the results set out below:
w (%)
5.6
6.8
7.8
8.0
8.5
9.0
9.5
MCV
13.3
13.5
13.7
13.1
11.1
8.5
6.0