Geology Reference
In-Depth Information
Table AE-1.1
LIKELIHOOD
CONSEQUENCE
TITLE
DESCRIPTION
SCALE
TITLE
DESCRIPTION
SCALE
Catastrophic
Total loss of a section
of tunnel
5
Likely to occur during
the construction of the
tunnel, possibly on
more than one
occasion
Major damage or
delay to tunnel or
major
environmental
impact affecting
programme
Probable
3
Critical
4
Some damage or
delay to tunnel or
some
environmental
impact affecting
programme
Serious
3
Likely to occur at least
once during
construction
of the tunnel
Occasional
2
A routine
maintenance repair
to tunnel or minor
hindrance
Marginal
2
Unlikely to occur
during construction of
the tunnel
Remote
1
Of little consequence
to programme
Negligible
1
Risk assessment
The assessment of risks associated with the use of a shielded
TBM was carried out separately from that for drill and blast
excavation.
Table AE-1.3 provides a brief summary of the hazards identi
ed for
a drill and blast option with level of probability of occurrence and
likely consequence and hence risk. Possible ways of mitigating the risk
are identi
ed. The original reports
go into far more detail of the nature of hazards, ways to mitigate
them and the potential ways those mitigation measures might prove
unsuccessful leaving residual risks. An example of a summary hazard
and risk register for this project (TBMoption) is given at Appendix E-2.
ed and the residual likely risk identi
Conclusions
It was found that the number of hazards and residual risks associated
with a shielded TBM construction would be greater than for the drill
and blast method. The principal reasons were:
the relative in
exibility of mechanised excavation and lining sys-
tems to deal with conditions for which they may not have been
speci
-
cally designed.
 
 
Search WWH ::




Custom Search