Information Technology Reference
In-Depth Information
Note that in the long chain each “SC” node must connect with at least ¸wo other
“SC” nodes, we have 2 m− 1
C .
In step 3, for given two short chains, if there are connected by link ( i 1 ,j 2 )in
the minimum “spanning tree”, we find another link ( i 2 ,j 1 ) such that :
( i 2 ,j 1 )=arg i,j min d i 1 j 2 + d ij −d i 1 j −d ij 2 : x i 1 j = x ij 2 =1 .
k =1 D k
Then we merger these two short chains into one big chain by adding link ( i 2 ,j 1 )
and deleting links ( i 1 ,j 1 ), ( i 2 ,j 2 ) as shown in Fig. 2.
Fig. 2. Merger two short chains into one chain
Suppose that before merging these two short chains, the total cost is C ,now
the total cost is given as C + d i 1 j 2 + d i 2 j 1
d i 1 j 1
d i 2 j 2
C +2
d i 1 j 2 , because
of the quadrangle inequality assumption, i.e., d i 2 j 1
d i 1 j 2 + d i 1 j 1 + d i 2 j 2 .The
above analysis shows that the length of constructed long chain can be bounded
by C R +2 m− 1
k =1 D k
C + C =2 C . Thus, we give the following result.
Proposition 2. The proposed approximation algorithm is 2 -approximation al-
gorithm for the long chain design problem under QI assumption.
Proof. In the above analysis, we have shown that the proposed algorithm pro-
vides solution at worst 2 bounded by time optimal solution.
Next we only need to construct an worst-case instance. Consider the instance
where all m “SC” nodes are evenly distributed on the circle with radius R = m .
Suppose each “SC” node contains two plants and two products, which are close
enough such that the total cost within each “SC” node is less than m 2 . Figure
3. gives the “minimum spanning tree”. For large enough m , the objective value
obtained by the proposed algorithm can be estimated by
1)sin( π
m )+ m 1
1)sin( π
m )+ 1
C ( m )=2( m
m 2 =2( m
m .
On the other hand, for large enough m , the optimal long chain is obtained by
connecting all adjacent “SC” node, thus its objective value can be estimated by
 
Search WWH ::




Custom Search