Table 8.2 Severity of the impact caused by CRs
Phase in which
CR is received
Severity of impact caused by CR based on the type of CR
URS CR
SRS CR
Design
CR
Construction CR
User requirements
Nil
Nil
Nil
Nil
SRS
Medium
severity
Nil
Nil
Nil
Design
High
severity
Medium
severity
Nil
Nil
Construction
High
severity
High
severity
High
severity
1. Medium if the component is
already constructed
2. Low, if the component is
not yet constructed
Table 8.3 Impacted artifacts and the strategy for implementation of CR based on the phase
during which the CR is received
Phase in which
CR is received
Artifacts impacted
Suitable strategies for
implementation
User/software
requirements
phase
User/software requirements
documents
As and when received or when
convenient but before design is
started
Design phase
User/software requirements
documents and design documents
As an when received or when
convenient but before design is
completed
Construction
phase
User/software requirements
documents, design documents and
source code
As and when received or, retrofitted
or situational implementation
2. If the work on the impacted component is started but not completed, the CR
would be handed over to the team member (or members) carrying out the work
for implementation. The CR would then be incorporated into the deliverables.
3. If the work on the component impacted by the CR is completed, then the CR
would be kept pending to be implemented either at the end of the project or at a
convenient time, such as when some resources become free or a part of the
team is idle waiting for some approval or clarification and so on.
If the project was following a strategy of holding CRs and then retrofitting them
at a convenient point in time, the following steps would followed to implement the
CRs:
1. Each CR is further analyzed to determine the components and deliverables
impacted by it.
2. At the completion of analysis, CR implementation activities are consolidated
into packages normally by the component.
3. Work allocation would be made so that all CRs pertaining to one component or
one set of related components would be allocated to the same set of team
members.