Manufacturing/Production Area Documents
Check the:
1. Inspection start-up check list with the release
label (manufacturing side)
2. Batch manufacturing record for
a.
Ointment and cream: On the batch
manufacturing record check that
i. All the information regarding the
identity of the batch are correct
ii. Record is duly signed by the
manufacturing supervisor
iii. Information related to the machine
cleaning is complete with the
signatures of the worker
iv. Yield calculation is correct
v. Temperatures (fat phase, water phase),
all the timings of (homogenizer,
agitator), vacuum limits are present
on the record and are within the
range specified in the MFM
3. Was there any deviation from MFM, was
any corrective action taken, was it properly
documented, was PRC raised and made a
part of the batch document?
Remarks:
4. Batch yield in the final and at various
in-process stage is correct
5. Rejection verification at various stages
of processing