Table 11.5. EISB Cost for Case 2
Cost Element
EISB Cost ($)
Design
Pre-design sampling and utility survey
15,000
Laboratory studies
20,000
Groundwater modeling
20,000
In-field hydraulic testing
2,000
Detailed design
10,000
Permitting and reports (including bioaugmentation related)
13,000
Total design
80,000
Capital
Site preparation
2,000
Injection/monitoring well installation and development
23,500
Process equipment
9,000
Materials
12,000
Labor
13,000
Cost for bioaugmentation culture
4,000
Additional cost for injection of culture
4,000
Waste management and disposal
1,000
Reports
5,000
Total capital
73,500
Operation and Maintenance (per event every 3 years)
Amendment re-addition
25,000
Reports
2,500
Average annual O&M
9,000
Annual Monitoring Costs (for first 5 years)
Labor
5,000
Analytical, groundwater
7,000
Reports
10,000
Total monitoring (per year)
22,000
Annual Monitoring Costs (6-30 years)
Labor
2,500
Analytical, groundwater
3,500
Reports
5,000
Total monitoring (per year)
11,000
11.5.4.3 Cost Analysis for Case 3: Deep Barrier
The cost analyses for the three technologies considered in Case 3 are presented in Table 11.7 .
A summary of costs is presented in Table 11.8 .
As with the biobarrier in Case 2, the higher O&M costs are due to the need for amendment
additions every 3 years to provide a continuing supply of growth substrate for the dechlorinating