Environmental Engineering Reference
In-Depth Information
1
2
3
90°
4
90°
Prevailing wind direction
5
Item #
Component
Lightning brush
60-m tower
Anemometer
Wind vane
Temperature probe
Date logger
1
2
3
4
5
6
6
Notes:
• Mount 57.2-m anemometer booms just above top guy ring.
• Mount 47.4-m anemometer booms just above the second highest guy ring.
• Mount 32-m anemometer booms 1 m above guy ring attower neck down.
• Distances taken from the ground to the sensors (not booms).
Figure 5-5. A typical recommended mounting configuration for a 60-m tubular NRG TallTower.
Source: AWS Truepower.
the top and bottom anemometers is recommended. For example, if the top mon-
itoring height is 50 m, the lowest monitoring height could be 30 m, since the
ratio of the two is 1.66.
At projects with multiple monitoring stations (met towers or remote sensing), it
is useful to match one or more of the monitoring heights between the stations to
facilitate comparisons between them.