Hardware Reference
In-Depth Information
4.2
Verify the schedulability and construct the schedule according to the RM algo-
rithm for the following set of periodic tasks:
C i
T i
τ 1
3
5
τ 2
1
8
τ 3
1
10
4.3
Verify the schedulability and construct the schedule according to the RM algo-
rithm for the following set of periodic tasks:
C i
T i
τ 1
1
4
τ 2
2
6
τ 3
3
10
4.4
Verify the schedulability under RM of the following task set:
C i
T i
τ 1
1
4
τ 2
2
6
τ 3
3
8
4.5
Verify the schedulability under EDF of the task set shown in Exercise 4.4, and
then construct the corresponding schedule.
4.6
Verify the schedulability under EDF and construct the schedule of the following
task set:
C i
D i
T i
τ 1
2
5
6
τ 2
2
4
8
τ 3
4
8
12
4.7
Verify the schedulability of the task set described in Exercise 4.6 using the
Deadline-Monotonic algorithm. Then construct the schedule.