biochemical oxygen demand and total suspended solids permit limits. After six
weeks, the facility was also meeting ammonia limits. Since that time, the facility has
shown its ability to meet permit limits with influent temperatures as low as 4.6 °C.
Summary of Schedule Performance
Item
Contracted
Actual
Difference
Start Date
May 19, 2008
May 19, 2008
0 days
Treatment Facilities
Substantial Completion
Date
Aug. 19, 2009
Jan. 19, 2009
212 days ahead
of schedule
Solids Handling Facilities
Substantial Completion
Date
Aug. 19, 2009
May 1, 2009
110 days ahead
of schedule
The project experienced excellent cost performance, which was a result of fin-
ishing ahead of schedule as well as excellent field production, efficient scheduling
and sequencing, development of competitive bid packages, and achieving critical
milestones. During execution of the work, the District requested various enhance-
ments to the project. A total of four change orders were executed with two of the
change orders being deductive. The Fairplay Sanitation District finished the project
at essentially the original guaranteed maximum price of $5,051,030 despite having
enhanced the project with what equates to $232,400 of additional work.
 