47. Implement updated sizing program from SAP Note 1736976.
48. Implement updated checklist ABAP per SAP Note 1729988.
49. Implement updated BW ABAP Analyzer per SAP Note 1829728.
50. Implement pre- and post-migration/upgrade task lists per SAP Note 1734333.
51. Implement BW housekeeping task list per SAP Note 1829728.
52. Implement additional DMO recommended notes.
First guidance document
You can find additional DMO recommended notes in the SAP First
Guidance document located at http://tinyurl.com/DMO-FirstGuid-
ance .
53. Fill in parameters for the PCA task list SAP_BW_BEFORE_UPGRADE.
54. Execute the PCA task list SAP_BW_BEFORE_UPGRADE with the following op-
tions:
Save yourself some time!
Only the checks below should be executed in step 0. The rest of the
checks in this task list have already been executed during the house-
keeping phase, as part of Section 6.3.10 .
a. Delete aggregate data via deactivation.
b. Confirm we are at the user lock stage of an upgrade/migration.
c. Confirm BEx-request is released and removed from table RSADMINA.