g. This program deletes RSTT traces.
h. This program deletes BW statistical data.
i. Delete aggregate data via deactivation.
39. Confirm manual task in task list SAP_BW_BEFORE_MIGRATION with the follow-
ing options in the interim BW:
a. Confirm all end users are currently locked.
40. Execute PCA task list SAP_BW_BEFORE_MIGRATION with the following options
in the interim BW:
a. Confirm BEx request is released and removed from table RSADMINA.
b. Uncheck flags in order to skip replication and generation of source-dependent ob-
jects.
c. Stop RDA daemons and process chains.
d. Backs up the data of workspaces.
e. Delete temporary/interim data used for analysis process design.
f. Delete temporary BW tables.
g. Delete entries from the DDNT and DDNF tables.
h. Generate before export of system prior to a migration.
41. Create DDL statement for migration with program SMIGR_CREATE_DDL in the
interim BW.
42. Run program SMIGR_BIG_ROW_STORE_TABS (for row store tables) in the inter-
im BW.
43. Confirm rowstorelist.txt exists on the application server in the directory /root/
EXPORTS/<SID>.
44. Suspend all scheduled jobs (execute report BTCTRNS1) in the interim BW.
45. Disable source system RFC destinations in the interim BW.
46. In the interim BW, check, download, and install newer versions of software compon-
ents, including:
a. SAPinst
b. R3*
c. libDBSL
d. tp