9.
B. A pilot site is an actual live location for testing.
10. A. A prototype network is a subset of the design in an isolated environment.
11. B
12. A. Monitoring commands are not SNMP tools.
13. A and B
14. C and D. The other answers are technical constraints.
15. A, C, and E
16. B, D, and F. The other answers are organizational goals.
17. A, B, D, E. Answers C and F are not usually included in the design document.
18. i = D, ii = C, iii = B, iv = F, v = E, vi = A, vii = G
19. C. The network health analysis is based on statistics obtained from the existing
network.
20. C. WAN circuits with sustained utilization of more than 70 percent should have their
provisioned bandwidth increased.
21. A, B, C, D, E. All these items are included in a network audit report.
22. B, C, and D
23. B
24. C, D, and E
25. B, C, and D
26. B
27. (1) Ident ify c u stomer requirements.
(2) Define upper OSI layers.
(3) Gather additional information.
(4) Choose underly ing technolog y.
28. B, D, and E
29. C-1, A-2, B-3, D-4. Taking a top-down approach the order of importance is security
design, IP addressing (network layer) design, physical topology design, and then net-
work modular design.
30. C and D
31. A, B, C, and D
32. C
33. A, B, and E