Fig. 6. Number of objective function calls of the two procedures vs number of time
intervals. The number of LP problems solved by AIS-LP is linearly dependent on time
discretization.
Fig. 7. One day electrical power profiles
values, or are slightly different. This fact shows that AIS-LP procedure converges
to the exact solution.
Figs. 7, 8 and 9 show the electrical and thermal power and energy storage
profiles of a one day scheduling.
The following remarks can be made:
a) the CHP starts early in the morning in order to store heat energy and satisfy
the first thermal load peak of the day. Excess electrical power is sold to the
external network;