TABLE 8.3
Categories of Projects Subject to Japan's Environmental Assessment Law
Class 1 Project
(EIA is always required)
Class 21 Project
(EIA required on case-by-case basis)
Category
Subcategory
Roads
National expressway
Metropolitan expressway
National roads
Large-scale forest roads
All
4 lanes or more
4 lanes or more and 10 km
2 lanes or more and 20 km
4 lanes or more and 7.5-10 km
2 lanes or more and 15-20 km
Waterways
Dams and weirs
Diversion channel
Lake development
Reservoir
100 ha
Land altered
>
Reservoir 75-100 ha
Land altered 75-100 ha
Land altered 75-100 ha
>
100 ha
Land altered
>
100 ha
Railway
Super express train railway track
All
>
10 km
7.5-10 km
Airport
Runway
>
2.5 km
Runway 1.8-2.5 km
Power plant
Hydraulic power plant
Thermal power plant
Geothermal power plant
Nuclear power plant
>
30 MW
22.5-30 MW
112.5.5-150 MW
7.5-10 MW
>
150 MW
>
10 MW
All
Waste disposal
>
30 ha
25-30 ha
Landill and reclamation
>
50 ha
40-50 ha
Land readjustment
>
100 ha
75-100 ha
New residential development project
>
100 ha
75-100 ha
Industrial estate development project
>
100 ha
75-100 ha
New town infrastructure development
projects
>
100 ha
75-100 ha
Distribution center complex
development project
>
100 ha
75-100 ha
Residential or industrial land
development by speciic organizations
>
100 ha
75-100 ha
Port and harbor planning
300 ha NA
Source: Adapted from Japanese Ministry of the Environment, Environmental impact assessment in Japan, www.env.go.jp/en/policy/assess/pamph.pdf. Accessed
July 19, 2013.
>