10. Select the view, and click the Move button on the Modify | Viewports
contextual tab. Click the horizontal C grid line to start the move, and
click the first horizontal guide grid line near the bottom of the titleblock.
Click the Move button again, and select a point on vertical grid line 1 to
start the move. Click the first vertical guide grid line at the left of the
titleblock within the bounds of the titleblock. Be sure to move
horizontally so that the C grid line stays aligned with its guide grid line,
as shown in Figure 23.21 . (Note that you can also snap to the
intersection of a datum element and the Guide Grid.)
Figure 23.21 Alignment of grid lines to the guide grid
11. Open the M-102 sheet, and drag the 2 - Mech floor plan view onto the
sheet. Click the Guide Grid button on the View tab, choose the existing
Floor Plans guide grid, and click OK, as shown in Figure 23.22 . Repeat
step 10 to align the view to the guide grid.
Figure23.22 Assign Guide Grid dialog box
12. Open the Sheet List schedule by double-clicking it in the Project
Browser. Click the Insert button on the Rows panel of the ribbon and
select the Data Row option. In the schedule, change Sheet Number to
 
 
 
 