Figure 10.45 Duct Pressure Loss Report Settings dialog box
Using the Duct Routing Tools
Now that you have reviewed the process of using the duct routing tools, you
will learn how to apply them in a simple exercise:
1. Open the Chapter10 _ Dataset.rvt file found at www.sybex.com/go/
masteringrevitmep2015 .
2. Open the floor plan view 1 - Mech, as shown in Figure 10.46 . You can
see that there are four air terminals (level hosted) mounted at 8′-0″
(2400 mm) above level and a VAV unit mounted at 11′-0″ (3300 mm).
These have already been connected to a supply air system.
Figure 10.46 Plan view
 
 
 