Upgrade Key Post-Steps
The following are some of the key post-steps after the technical upgrade is completed suc-
cessfully:
• Stop and start the SAP system to make sure it is coming up without problems.
• Schedule the background jobs.
• Import the correct profiles in transaction code RZ10.
• Execute SGEN to generate all the ABAP loads. Set parallel processes so that SGEN
will run faster.
• Perform post-steps as per the upgrade guide.
• Perform any customer-specific steps.
• Take a complete offline backup.