TABLE 4.4
Permits, Certifi cates, and Report Requirements for a Small Gold Mine in Indonesia (as of 2004) - The Bankable Feasibility Study
together with the Environmental Impact. Assessment are very much umbrella approvals. The mine operator has to secure a wide range of additional specifi c permits and certifi -
cates before mine construction can begin
Company
1. Foreign Investment Approval Model IPMA (SPPP)
2. Articles of Association (Establishment Deed)
3. Establishment Deed Legalization
4. Company Domicile Permit (Surat Izin Tempat Usaha/SITU)
5. Taxpayer Registration Code Number (NPWP)
6. Affi rmation of Taxable Company (PKP)
Manpower
7. Registration of Company at Manpower Department
8. Approval for Deviation from Standard Working Hours
9. Legalization of Company Regulations (two yearly renewal)
10. Establishment Worker's Union (SPSI - Kesepakatan Kerja Bersama)
11. Collective Labour Agreement (CLA)
12. Manpower Insurance and Social Benefi t (JAMSOSTEK)
13. Occupational Health
14. Expatriate Utilization Plan Approval (RPTKA-Rencana Penggunaan Tenaga Kerja Asing)
15. TA-01 Recommendation for Expatriate Visa - VBS
16. Travelling Permit (SKJ - Surat Keterangan Jalan)
17. Temporary Resident Visa (VBS - Visa Berdiam Sementara)
18. Temporary Entrance Regional Immigration Permit (KITAS - Kartu Izin Tinggal Terbatas)
19. Work Permit for Expatriates (IKTA - Izin Kerja Tenaga Kerja Asing)
20. Tax Registration for Foreigners (PBA)
21.
Certifi cation of Registration for Temporary Resident for Expatriates (SKPPS - Surat Keterangan Pendaftaran Penduduk Sementara)
22.
SKTTS - Surat Keterangan Tempat Tinggal Penduduk Sementara
23.
Multiple Exit Reentry Permit (MERP)
Environmental Assessment/General Permits
24. Environmental Impact Assessment (AMDAL) Approval
25. Permit to Conduct General Mining Activities in Forest Areas
26. Appointment of Kepala Teknik & Wakil Kepala Teknik
27. Location Permit (Izin Lokasi)
28. Building Utilization Right Certifi cate, permission to use the land for project (HGB)
29. Building Construction Permit (IMB)
30. Deep-Well Drilling Permit for industrial purpose (SIPA)
31. Limited Importer Identifi cation Number (APTI)
32. Master List/Approval to import the materials and equipment and obtain the duty exemption
33. Import Duty and VAT exemption (postponement to pay value added tax of M/L importation)
34. Material Import Identifi cation (RIB)
35. Permits for Temporary Import of Construction Equipment
36. Pressurized Equipment Certifi cation (included in this category gas cylinders, transport vessel, air conditioning, vessel or storing gas, mixture of gas, liquid,
etc.) (Reg. No. PER 01/MEN/1982)
37. Inspection and Testing of Power Machine and Production Machines (included in this category motors, turbines, working tool machines, genset,
transmission, casting, pressing, piping, crushing, rolling, cutting, furnaces, trolley, etc.) (Reg. No. PER01/MEN/1985)
38. Inspection and Testing of Lifts and Transport Equipment (included in this tackles, pneumatics, gondolas, cranes, escalator, conveyors, towing, truck, tractor,
forklifts, locomotive, etc) (Reg. No. PER02/MEN/89)
39. Lighting Conductor Circuit Installation Approval (Reg. No. PER02/MEN/89)
40. Automatic Conductor Circuit Installation Approval (Reg. No. PER02/MEN/89)
41.
Portable Fire Extinguisher Installation and Maintenance Approval
42.
Quarry Permit (S. I. P. D) Izin Bahan Galian C