Civil Engineering Reference
In-Depth Information
P
180
180
180
35
150
1 50
150
250
1 50
250
1 00
35
30 recess
150
260
150
200
200
200
Mortar base
Reinforcement:
10 mm diameter ribbed bars
Steel section:
254×254×89 kg UC
100
600
Figure 2.18 Standard push-off test specimen specified in EC4 [ 2.37 ] .
reinforcement specified and the size of the slabs are greater than that of the
earlier British Standard push-off test [ 2.38 ] shown in Figure 2.19 .EC4
[ 2.37 ] gives results that are less influenced by splitting of the slabs and so give
better predictions of the behavior of connectors in beams as mentioned by
Johnson [ 2.39 , 2.40 ] .
2.6.3 Complete and Partial Shear Concoction
The connection between the steel beam and the concrete slab is called
“complete” in the sense that the slip and uplift at the interface of the two
elements are negligible. Shear connection in composite beams is identified
[ 2.41 , 2.42 ] as complete when the beam has a bending strength that would
not be increased by the addition of further connectors. On the other hand,
the connection between steel beam and concrete is called partial when
fewer connectors are used than are required for the complete shear connec-
tion. The term “partial connection” should not be considered to imply
 
 
Search WWH ::




Custom Search