CR movement lower performance range
value (in lower limit switch position).
In case of simultaneous entry of commands
from group control key and fifth group control key
at the SHC RG&IC-R input, only group control
command is performed.
Distribution of CR by groups, sequence of
groups movement and priorities of control func-
tions performing in case of simultaneous perform-
ing of several functions at the SHC RG&IC-R input
are defined by rod group and individual control
algorithms, which are set in the reactor design.
SHC RG&IC-R realizes priorities of control func-
tions performance used at the Ukrainian power
units with WWER-1000 reactors:
Information Functions
• Displaying: coordinates of CR selected by
the operator for individual control; number
of group selected for manual group con-
trol; number of main (work) group and CR
auxiliary group while their moving in the
design order;
• Indication of movement direction (lift or
lowering) of the moving CR or CR group;
• Monitoring of all CR position within the
operating cycle stroke range (between LLS
and ULS) and identiication of two end and
ten intermediate position of each CR;
• Monitoring and displaying of the precise
(with 1% discretion) vertical position: se-
lected by the operator CR or selected CR
group; main (work) CR group while mov-
ing in the design order; each CR group
(intermediate position); all CR in one (any
one selected by the operator) group;
• Monitoring of vertical mismatch of all CR
in each group and sending of alarm mes-
sage led by sound signal in cases when po-
sition of, at least, one CR deviates for more
than ± 40 mm of the middle position of the
group, which this CR to constituent;
• Detection of fall of, at least, one (any) CR
into the core and sending of the signal,
which initiates forming of PRP2 command,
to the irst and second SHC E&PRP sets;
Emergency Reactor Protection: In re-
lation to the other functions: when ERP
commands is received, it is performed im-
mediately, after that performance of other
control functions is suspended and can be
renewed only after ERP command cancel-
lation at the SHC RG&IC-R input;
Accelerated Preventive Protection: In re-
lation to the other control functions except
emergency reactor protection: when RAPP
command is received, it is performed im-
mediately, after that reactor power unload-
ing (RPwU) command must be performed;
Preventive Reactor Protection PRP1: In
relation to the other control functions ex-
cept ERP and RAPP: during PRP1 com-
mand performance of B↑ and D↓ automatic
regulation and manual control commands
is blocked (RPwU command performs the
same actions as PRP1);
Preventive Reactor Protection PRP2:
In relation to any actions, which prescrip-
tive upward movement of any groups or
separate CR: during PRP2 command per-
formance of B↑ automatic regulation and
manual control commands is blocked;
Downward Movement of Any Groups or
Separate CR: In relation to any actions,
which prescriptive their upward movement.
Forming and sending to the in-core reactor
monitoring system (IRMS) of data on the
precise vertical positions of all CR;
Forming and sending to power unit com-
puter information system of messages with
data on: group control commands, initiated
by the operator and / or received from the
adjacent systems; coordinates of control