Site fabricated timber panels positioned on ground floor slab by an hydraulic lifter.
Wall panels handled and fixed in position within a four hour period by two joiners,
one labourer and the site manager.
Eighteen wall panels make up the complete ground floor plan of a semi-detached
house unit.
14.11 Comments on the organisation and management of
business
The principal/ director of this housebuilding company has - “GOT IT RIGHT!”
The business has reliable clients, who pay promptly each month and a good work-
ing relationship exists between them.
A high degree of trust exists between the client and the contractor and future
development projects are being jointly worked on. This should ensure continuity
of work for the business.
At the current time, the private/ speculative housing market is buoyant and
encouraged by the government's - “help to buy scheme” and the banks releasing
more mortgages.
The principal/ director is directly involved in the site management of his projects.
A stable subcontractor labour force is employed which will need to be expanded
as additional projects commence.
As further developments come on stream, the contractor will have to consider
recruiting site management personnel (i.e. additional site managers).
Turnover currently is in the order of £100,000 per month, over expansion of the
company will have to be carefully monitored.