BUXTON ROAD - 9 Units
(Sequence of construction)
Heras
Fensing
Double garage
to be built
as site store
Area of
house units
8/9 to be used
as site compound
Scheme layout.
Buxton Road - 9 units (sequence of construction)
Site strategy
The build sequence is shown for houses 1 to 9.
The access road is to be constructed to base course level prior to commencing the
foundations work.
A double garage (marked block G) to be constructed in order to be used as a
secure lock up store for the project.
Ground floor slabs for units 5, 6 and 7 to be completed. Block 7 is to be used as a
fabrication area for the site manufacture of the timber frame wall and floor panels.
Completed panels to be stored on block 5 and 6 prior to erection by safe handler.
Temporary site office and plant and materials store (marked 1 and 2 on the layout
plan) to be provided together with attached toilet facilities.
Completed timber framed panels to be stored on the ground floor slab areas of
blocks 5 and 6 prior to erection.