Civil Engineering Reference
In-Depth Information
14.1 Contents of the case study
Evidence of a well planned project
The establishment of a small building firm is outlined in this chapter. The company
described, undertakes construction work for two property development clients. The
managing director's background experience is outlined and his approach to manag-
ing a small housing contract clearly shown.
The following aspects are covered:
The responsibilities of the principal director and his quantity surveyor/ office
administrator are outlined.
Images of the office facilities for a small contractor are shown.
The approach to establishing the site facilities for a development of nine housing
units is illustrated. A site layout plan is shown for the project.
The site strategy is outlined for the project in relation to the planned building
sequence and site layout plan.
The sequence of construction for a semi-detached timber framed unit is illustrated.
The images are shown of the foundations and ground floor slab construction. The
Search WWH ::