Glulam timber frame - erection sequence
10 bays @ 6m
Bay 7
2d
Bay 4
2d
Bay 1
3d
Bay 8
2d
Bay 5
2d
Bay 2
3d
Bay 9
2d
Bay 6
2d
Bay 3
3d
Overall duration for glulam frame erection-21 days
(contract programme allowance 20 days)
Plan of main store Glulam frame