NAME AND SHAME BOARD
DATE
LOCATION
OCCURANCE
SUBCONTRACTOR
Tu e
15th Sept
Drainage work
MH 7-9
(rear block 3)
Inadequate support to
drainage trenches
Evans drainage
company
Barriers failed to be erected
at end of day
Wed
16th Sept
First floor
landing &
corridor areas
Work area left in an
uncleared state
- timber off cuts/
loose timber
B & R joinery
Wed
16th Sept
Perimeter scaffold
2nd floor
front elevation
Missing toe boards and
handrails to staircase exit
(area to be cordoned off)
- untill dealt with
HR scaffolding
1.8 The site manager
Knowledge requirements
To be familiar with site procedures.
To deal with site induction process for own labour and subcontractors and visitors
To deal with requirements outlined on method statements and risk assessments
prior to commencing operations on site
To keep and maintain site records with respect to progress, contract delays and
variations to contract
To understand contact procedures regarding the issue of permits
To be computer literate with respect to computerised processes to aid the con-
struction manager - extensive company procedures are transferable from the
companies website, e.g. health and safety policy, method statements and risk
assessment formats
To understand basic programme techniques including progress recording
Management skills
To develop communication skills with operatives and subcontractors when issuing
instructions
To show evidence of computer competency in order to maintain site records and
access company procedures
To show competency in the organisation of subcontractors