Positioning top and bottom of panels from cherry pickers
External elevation of building showing secondary cladding
External cladding logistics
The project reflects inovative handling and fixing techniques for the exterior facade
of a medium rise building. The mixed use of a small hydrolic crane working three
floors above the panel fixing level is a well established technique.
The logistics of handling wall panels to the floor 7 and 8 using a single track mono-
rial system is even more innovative.